Road Permits
You need permission from us if you want to occupy part of a road, path or car park. You also need permission to carry out work on a road or car park.
Application to occupy a road or car park
You may want to occupy part of the road by:
- using a skip
- putting up scaffolding
- displaying a hoarding or signage
- storing building materials
Applications require at least 10 working days notice and in some cases may require 28 days notice.
Application to carry out work on a road or car park
You may want to carry out work such as:
- excavations
- constructing a new access
- repairing apparatus under the road
- laying new pipes
Applications require at least 10 working days notice and in some cases may require 28 days notice.
Charges
There is a charge for different types of occupation or work. Failure to pay for work in advance will mean the fee is doubled unless otherwise agreed. Once an application has been received a member of the Road Network Team will contact you to arrange payment of the correct fee.
Roads (Scotland) Act 1984 Permissions | |||||
Section | Title | Description | Charge | ||
in advance | in arrears | ||||
56 | Control of works and excavations (standard works,eg private driveway crossings of footway) | Occupation of road to undertake works within the road boundary (see below for additional charge for s.109 works) | Initial Permission | £152 | £304 |
Renewal | £66 |
| |||
| Control of works and excavations (minor / other standard works) | Initial Permission | £250* | £500 | |
| Renewal | £100 |
| ||
| Control of works and excavations (major works) | *Additional charge of £150 for works exceeding 10 working days | Initial Permission | £500* | £1,000 |
| Renewal | £125 |
| ||
58 | Occupation of parts of the road for deposit of building materials etc | Deposit of materials | Up to 4 weeks | £109 |
|
Subsequent 4 week periods or part thereof | £109 |
| |||
Erection of staging or scaffolding | Less than 1 week | £109 | £218 | ||
Up to 12 weeks | £142 | £284 | |||
Subsequent 12 week periods or part thereof | £109 | £218 | |||
59 | Road occupation (Control of obstructions in roads) | Occupation of road by street cafe |
| £109 |
|
Other road occupation - less than 100m² | Up to 4 weeks | £142 |
| ||
Other road occupation - each additional 100m² or part thereof | Subsequent 4 week periods or part thereof | £138 |
| ||
85 | Control of builders' skips on road | Deposit of a skip | Initial Permission | £142 | N/A |
Section | Title | Description | Charge | ||
---|---|---|---|---|---|
in advance | in arrears | ||||
109 | Permission to execute roadworks | Permission to install apparatus in a road (non PU) | Initial Permission | £254 | £508 |
Renewal | £64 |
Contact details
Get in touch with for more advice:
- Email streetworks@dumgal.gov.uk
- Call 030 33 33 3000